Back to The BriefThe Brief · Rail weather monitoring

Ten mast-mounted weather stations give rail teams local readings

Network Rail’s Wales and Borders route is the first in the organisation to put weather stations on existing railway communications masts.

Louise Pryce ·

Archive: Whitland railway station on 6 June 2009. Nigel Thompson / Geograph and Wikimedia Commons, CC BY-SA 2.0; framed. Whitland is a listed monitoring location; the photograph does not show the new equipment.

Archive: Whitland railway station on 6 June 2009. Nigel Thompson / Geograph and Wikimedia Commons, CC BY-SA 2.0; framed. Whitland is a listed monitoring location; the photograph does not show the new equipment.

Original photographCC BY-SA 2.0

Ten weather stations have been installed on existing railway communications masts across the Wales and Borders route, giving Network Rail local readings from the lines it manages. The infrastructure owner announced the deployment on 14 October. It says this is its first route to use GSM-R railway communications masts for the equipment.

The ten monitoring locations

10 figures

1
Whitland
2
Llantwit
3
Cilmeri
4
St George’s
5
Trewyn
6
Craven Arms
7
Gobowen
8
Glantwymyn
9
Llanrwst
10
Buckley

Source: Network Rail

Readings directly from the railway

The stations measure rainfall, wind speed and direction, temperature, humidity and air pressure. Network Rail says the sites fill monitoring gaps in places vulnerable to severe weather. The readings will supplement the forecasts it receives from MetDesk. The intended benefit is more targeted decisions about inspections, response teams and measures such as speed restrictions. The announcement does not establish how much passenger delay the new equipment has prevented.

Storm costs and autumn preparations

Network Rail says 25 named storms affected the route between February 2023 and January 2026. For storms with complete performance data, the average was more than 38 hours of delay and £179,000 in train performance costs. It does not give the number of storms with complete data. A separate joint autumn-preparations announcement on 9 October set out plans for four treatment trains to cover more than 54,400 miles of track. Those planned treatment miles are separate from the new monitoring sites.

Background and supporting figures

Where this sits

2 checked facts

  1. How does it compare?

    • New readings supplement MetDesk forecasts to inform operational response. No measured delay reduction claimed.

      networkrailmediacentre.co.uk

    • 25 named storms February 2023–January 2026; average >38 hours and £179000 only where complete data available, denominator unstated. No extrapolated total.

      networkrailmediacentre.co.uk

Every line above was checked against the source named beside it before this piece was published.